Summerleas Road Underpass – Update

Excavation for the underpass is now complete.

The base layer for the underpass floor and ramps will be prepared next week.

Installation of electrical and drainage conduits will occur during the base slab preparation.

The program for the following few weeks will include pouring the base slab.  After the curing period, the new box culvert sections that form the underpass will be installed. The duration of this work is weather dependent.